Integration Wizard Preferences
Use this dialog box to select the options when importing data into Cobra.
Contents
Field | Description |
---|---|
Apply historical budget changes as an adjusting entry in the current status period | Select this option if you are importing budget data. This option directs Cobra to maintain historical data and to summarize changes being loaded into historical periods as a single record in the status period. |
Apply historical forecast changes as an adjusting entry in the current status period | Select this option if you are importing forecast data. This option directs Cobra to maintain historical data and to summarize changes being loaded into historical periods as a single record in the status period. |
If the work package is due to start in the current period, the spread will be the same as the budget and the Calculate Forecast process will just move the spread if it slips. If the work package has started, the budget will be dropped during the Calculate Forecast process if the forecast uses the retain EAC method. Cobra will take the value into account for the retain EAC forecasts and run the respread process normally. | |
Cobra assumes that before you select this option, you have already advanced the calendar but have not yet calculated the forecasts. If forecasts have been calculated after advancing the calendar before applying the historical forecast changes, you need to recalculate forecasts after selecting this option. | |
Force existing Work Package baseline dates to match the schedule | Select this option to update the work package baseline dates to match the dates of the mapped activities to the date set selected for Baseline Dates on the Schedule Mapping page of the Integration wizard.
|
Update Control Account dates to span Work Package dates exactly | Select this option to update the control account start and finish dates for all date sets to exactly match the earliest start and latest finish dates of all work package date sets.
|
Update the description for existing Control Accounts and Work Packages | Select this option to update the description of existing control accounts to match the description of the activity in the corresponding activity file. If the description in Cobra is blank, Cobra still updates it whether you select this check box or not. |
Recalculate existing milestone weights | Select this option to recalculate the weight of each milestone. This option applies only if Cobra calculates milestone weights during the import process and not imported from a file field. |
Delete items from Cobra that are no longer in the schedule | This option directs Cobra to delete data during the integration. |
Selecting the
Secure check box for this option while the
Selected check box is cleared also selects the
Secure check box for any of the following options:
Selecting the
Secure check box for this option while the
Selected check box is selected does not affect the
Secure check box for any of the following options:
Clearing the
Selected check box for this option while the
Secure check box is cleared does not affect the
Secure check box for any of the following options:
Clearing the
Selected check box for this option while the
Secure check box is selected also selects the
Secure check box for any of the following options:
Cobra determines what data to delete using the sub options.
This option controls whether deleted items should be listed in the log file:
| |
Delete only items that satisfy the selection criteria | Select this option to delete only the items from Cobra that meet the criteria selected. This option displays only when loading into an existing project. |
Load only schedule activities that do not exist in Cobra |
Select this option to import only new data and to ignore any existing data so that previously imported data remains the same. Selecting or clearing the Secure check box for this option also selects or clears the Secure check box for the Load only date for Control Account that already exist in Cobra option, except if this option is disabled in the EPM SA. |
Load only data for Control Accounts that already exist in Cobra | Select this option to import only data previously imported and to ignore any new schedule information. Selecting or clearing the Secure check box for this option also selects or clears the Secure check box for the Load only schedule activities that do not exist in Cobra option, except if this option is disabled in the EPM SA. |
Create Work Package that do not exist when loading forecast | Select this option to create new work package if it does not exist and you are loading forecast data. If this option is not selected, Cobra will ignore forecast values if the work package does not exist. |
Selected | Select this check box for any of the options to make the option selected by default in the process wizard where it is located. |
Secure | Select this check box for any of the options to prevent users from changing the setting for that particular option in process wizards where these options are also located. Cobra uses this feature to secure certain options while users run processes against projects.
If the Secure check box is selected, this option cannot be modified on the options pages of the Cobra process wizards. Select this option to ensure that all users are using the same settings when running Cobra processes. |